SR-14 Construction Update- July 20, 2012

Last modified on Oct 17, 2013

New Signals Installed at MP 9.7 & 17 The Restore14 project is now 79% complete. Work is underway at Mileposts 9.7 and 17 and crews have reduced the roadway to one lane at these locations in order to perform the repair work safely. Traffic signals are in place at each location to help facilitate traffic flow during the open hours. The roadway continues to open each weeknight from 7 p.m. until 7 a.m. and on weekends from 5 p.m. on Friday until 7 a.m. on Monday. Please use caution and follow the traffic signals at all times.

At MP 7.5, the main slide site, workers are addressing additional movement on the west end of the slide area. Major excavation is ongoing to remove landslide material.

At MP 9.7, crews have removed guardrail and started excavation operations. Workers are fabricating forms and starting to install rock anchors to safely reconstruct the tunnel that runs under the roadway.

At MP 17, construction crews will install a 200-foot long soldier pile wall to keep the roadway in place. Workers have completed a test drilled shaft and have begun installing beams for the wall.

Please check www.udot.utah.gov/traffic for the most up to date traffic information.

More Articles


Physical Address
705 East Movie Ranch Road
Duck Creek, Utah  84762

Mailing Address
26 North Main Street
Cedar City, Utah  84720

Website
www.UtahMountains4sale.com
Email
Sold@UtahMountains4sale.com
Toll Free
877-809-6843
Evelyn Cell
435-691-9753
Alonzo Cell
435-590-3847
Fax
435-867-1116

ASK FOR “The Ashworth Team”
Evelyn & Alonzo Ashworth
Coldwell Banker Majestic Mountain Realty

Follow The Ashworth Team on Twitter